The obligation
Designers must prepare and provide a safe design report (construction safety report) to the commissioning PCBU, covering hazards, risks and controls for the structure's lifecycle, for onward provision to the principal contractor.
The WHS Regulation (SA) requires designers to provide a construction safety report to the PCBU who commissioned the design, to be passed to the principal contractor. The Code of Practice: Safe Design of Structures specifies what information the report should contain, including hazard identification, risk assessments, recommended controls and residual risks for construction, operation, maintenance and demolition phases. Best practice is to address all lifecycle stages.
What
Designers must prepare and provide a safe design report (construction safety report) to the commissioning PCBU, covering hazards, risks and controls for the structure's lifecycle, for onward provision to the principal contractor.
Source
safeworkaustralia.gov.au

Full analysis

Free account

What this means for you

Free account

Read the full analysis, tailored to your industry

  • Impact summary tailored to your industry
  • Full plain-English analysis of what changed
  • Email alerts & digests when this law changes
  • Compliance self-assessment tools
Labels
safe design report construction safety report designer principal contractor
Official sources
Frequently asked questions

Which WHS law does this come from?

Safe design report — mandatory information provision is a WHS requirement set out in Safe design of structures (SA). It is made under Work Health and Safety Act 2012 (SA). The relevant provision is Safe design of structures > Safe design report § 4.

What does this WHS obligation require?

Safe design report — mandatory information provision is a WHS obligation under Safe design of structures (SA). In short, Designers must prepare and provide a safe design report (construction safety report) to the commissioning PCBU, covering hazards, risks and controls for the structure's lifecycle, for onward provision to the principal contractor.

What changed recently?

Safe design report — mandatory information provision was last updated on 26 August 2026.