The obligation
PCBUs and persons with management or control must ensure erection and dismantling is performed by competent persons following the manufacturer's instructions and an engineered methodology.
The Code requires that erection, jumping, and dismantling of tower cranes be carried out only by competent persons, in accordance with the manufacturer's instructions or an engineer-approved methodology. A written erection and dismantling plan must be prepared. The PCBU must ensure adequate supervision and that all persons involved hold relevant high-risk work licences (dogging/rigging) as required under the WHS Regulation.
What
PCBUs and persons with management or control must ensure erection and dismantling is performed by competent persons following the manufacturer's instructions and an engineered methodology.
Source
worksafe.qld.gov.au

Full analysis

Free account

What this means for you

Free account

Read the full analysis, tailored to your industry

  • Impact summary tailored to your industry
  • Full plain-English analysis of what changed
  • Email alerts & digests when this law changes
  • Compliance self-assessment tools
Labels
tower crane erection dismantling high-risk work licence competent person
Official sources
Frequently asked questions

Which WHS law does this come from?

Erection and Dismantling of Tower Cranes is a WHS requirement set out in Tower crane code of practice 2017 (QLD). It is made under Work Health and Safety Act 2011 (QLD). The relevant provision is Tower Crane Code of Practice 2017 > Erection and Dismantling § 3.

What does this WHS obligation require?

Erection and Dismantling of Tower Cranes is a WHS obligation under Tower crane code of practice 2017 (QLD). In short, PCBUs and persons with management or control must ensure erection and dismantling is performed by competent persons following the manufacturer's instructions and an engineered methodology.

What changed recently?

Erection and Dismantling of Tower Cranes was last updated on 26 August 2026.

About this Topic

Updates trackedMonitoring
Monitoring detail
First seenAug 2026