The obligation
Chapter 8 of the Code sets considerations for erecting, dismantling and using scaffolding near electric lines up to and including 33 kV A.C.
Where scaffolding work involves voltages above 33 kV A.C., consultation with the electricity supply authority is mandatory and any specified conditions must be complied with. For guidance, the Code refers to AS 4576:2020 Guidelines for scaffolding and the SafeWork NSW Scaffolding Industry Safety Standard. These prescribe a 4-metre approach distance for conductive material scaffolding near electric lines.
- What
- Chapter 8 of the Code sets considerations for erecting, dismantling and using scaffolding near electric lines up to and including 33 kV A.C.
- Source
- safework.nsw.gov.au
description
Full analysis
lock
Free account
tips_and_updates
What this means for you
lock
Free account
lock_open
Read the full analysis, tailored to your industry
- star
Impact summary tailored to your industry
- check_circle
Full plain-English analysis of what changed
- check_circle
Email alerts & digests when this law changes
- check_circle
Compliance self-assessment tools
Frequently asked questions
Which WHS law does this come from?
Scaffolding near electric lines (NSW Code chapter 8) is a WHS requirement set out in Work near overhead power lines (NSW). It is made under Work Health and Safety Act 2011 (NSW). The relevant provision is Work Health & Safety > Codes of Practice > Electrical Safety > Scaffolding.
What does this WHS obligation require?
Scaffolding near electric lines (NSW Code chapter 8) is a WHS obligation under Work near overhead power lines (NSW). In short, Chapter 8 of the Code sets considerations for erecting, dismantling and using scaffolding near electric lines up to and including 33 kV A.C.
What changed recently?
Scaffolding near electric lines (NSW Code chapter 8) was last updated on 11 October 2026.