Four-Step Risk Management Process for PCBUs

Code version as at 1 Aug 2019 From How to manage work health and safety risks, no changes tracked yet
Medium severity
NSW · Work Health and Safety How to manage work health and safety risks > Risk Management Process
The obligation
The Code prescribes a four-step process: (1) identify hazards, (2) assess risks, (3) control risks using the hierarchy of controls, and (4) review controls.
Under the Code, PCBUs must follow a systematic risk management process. Step 1: Identify hazards (sources of potential harm). Step 2: Assess risks—when required, evaluate the likelihood and consequence of harm. Step 3: Control risks using the hierarchy of controls (eliminate, then substitute, isolate, engineer, administer, PPE). Step 4: Review and maintain controls. Records of risk assessments must be kept. …
What
The Code prescribes a four-step process: (1) identify hazards, (2) assess risks, (3) control risks using the hierarchy of controls, and (4) review controls.
Source
safework.nsw.gov.au

Full analysis

Free account

What this means for you

Free account

Read the full analysis, tailored to your industry

  • Impact summary tailored to your industry
  • Full plain-English analysis of what changed
  • Email alerts & digests when this law changes
  • Compliance self-assessment tools
Labels
hazard identification risk assessment hierarchy of controls risk register record keeping
Official sources
Frequently asked questions

Which WHS law does this come from?

Four-Step Risk Management Process for PCBUs is a WHS requirement set out in How to manage work health and safety risks (NSW). It is made under Work Health and Safety Act 2011 (NSW). The relevant provision is How to manage work health and safety risks > Risk Management Process.

What does this WHS obligation require?

Four-Step Risk Management Process for PCBUs is a WHS obligation under How to manage work health and safety risks (NSW). In short, The Code prescribes a four-step process: (1) identify hazards, (2) assess risks, (3) control risks using the hierarchy of controls, and (4) review controls.

What changed recently?

Four-Step Risk Management Process for PCBUs was last updated on 6 October 2026.

About this Topic

Updates trackedMonitoring
Monitoring detail
First seenOct 2026